Construction Updates - 2024

Construction Update - 12 September

Construction Update - 12 September

The sunny spring days have allowed our builders to make good progress onsite.

Posted 13 Sep 2024
Construction Update - 26 September

Construction Update - 26 September

Excavation works continue at Level 0 of the new Stage 2 building, where the new kitchen, general services and "end of trip" staff facilities will be located. 

Posted 13 Sep 2024
Construction Update - 22 August

Construction Update - 22 August

The Stage 2 construction site is a hive of activity.

View PDF  
Posted 23 Aug 2024
Construction Update - 8 August

Construction Update - 8 August

Bulk excavation and piling works on the Child and Adolescent Mental Health Unit is also well progressed with the builders expecting to pour the concrete slab in the coming weeks. 

Posted 12 Aug 2024
Construction Update - 18 July

Construction Update - 18 July

The outline of the new Stage 2 building is beginning to take shape as concrete piling works progressed onsite.

Posted 18 Jul 2024
Construction Update - 4 July

Construction Update - 4 July

There is a flurry of activity at the site of the new Stage 2 building with the foundations of the new building starting to take shape.

Posted 04 Jul 2024
Construction Update - 20 June

Construction Update - 20 June

The first of two tower cranes supporting the delivery of the more than $1 billion Nepean Hospital Redevelopment has been installed.

Posted 20 Jun 2024
Construction Update - 6 June

Construction Update - 6 June

The Stage 2 site is gearing up for the installation of two tower cranes which will do all the heavy lifting during the concrete and steel structural work for the new seven-storey building. The cranes will be secured onto engineered concrete slabs in the middle of the site. 

Posted 06 Jun 2024
Construction Update - 2 May

Construction Update - 2 May

Excavation works at the footprint of the Stage 2 site is almost finished and foundation piling works are now underway.

Posted 01 May 2024
Construction Update - 4 April

Construction Update - 4 April

Construction is underway on the new Child and Adolescent Mental Health Services (CAMHS) Unit. The old Sexual Health building and Nepean 2 have been recently demolished to make way for CAMHS which will provide mental health care to young people aged between 12 and 17. 

Posted 03 Apr 2024
Construction Update - 21 March

Construction Update - 21 March

Works at the footprint of the Stage 2 site are progressing nicely with the pit now filled. Construction has also started on the new Child and Adolescent Mental Health Services (CAMHS) Unit.

Posted 21 Mar 2024
Construction Update - 29 February

Construction Update - 29 February

This construction update is a special edition dedicated to the completion of refurbishment and repurposing works.

Posted 28 Feb 2024
Construction Update - 15 February

Construction Update - 15 February

Bulk excavations at the footprint of the Stage 2 building is progressing well. The yellow Moits machines excavators have removed masses of cylindrical concrete piles that held up the old North Block 

Posted 15 Feb 2024
Construction Update - 25 January

Construction Update - 25 January

Refurbishment works across the campus are nearing completion with refurbished areas for Allied Health Clinical spaces, Allied Health Offices and Paediatrics Outpatients Unit on Levels 3 and 4 of Building C expected to open in the coming weeks. 

Posted 25 Jan 2024