Barber Avenue roadworks are underway which means there are changes to vehicle and pedestrian access and limited street parking.
Pedestrian and vehicle access to the Nepean Private Hospital, Tresillian and Somerset Childcare Centre will be maintained throughout the duration of the roadworks.
During the construction period along Barber Avenue, please drive slowly and pay close attention to traffic controllers and signage.
Please use the P1 and Nepean Hospital Private car parks.
The Barber Avenue link bridge also provides accessible, covered pedestrian access between the P1 car park, the Nepean Hospital and Nepean Private Hospital.
Detailed excavation works are continuing on Level 0 and Level 1 of the new Stage 2 building in preparation for the first concrete slab on ground.
Construction of a temporary loading dock at the northern end of Building D is progressing well with the concrete pour for footings now complete.
The temporary loading dock is expected to be completed in a few weeks.
Across the campus, scaffolding is being erected on the northern and western end of the site for the new Child and Adolescent Mental Health Services (CAMHS) Unit. The first slab of concrete is set to be poured in coming weeks.
More information:
Visit our dedicated project website
Explore our interactive map for the latest construction activities and best hospital access points